One bathroom out of service, a tile setter on a schedule, and a household still living in the house. Here is where the glass actually fits in your remodel and what to have ready before we measure.

Call (586) 315-8900
Remodels in Rochester

The Glass Comes Last, And That Surprises People

A remodel runs in a straight line: demolition, plumbing rough, waterproofing, tile, grout, then everything you can see. Glass sits at the end of that line and it cannot jump the queue. We measure the finished opening, which means after the tile is set and the grout is in. Plenty of homeowners assume the door is ordered alongside the tile so everything arrives together. It does not work that way, and knowing it in the first week is what keeps the last stretch of the project calm.

That is not the same as waiting until the end to talk to us. The decisions that shape your door happen early: how tall the curb is or whether there is one, which direction the door has to open and what sits in its arc, where the niche and the bench land, and whether the wall your hinges anchor to has anything solid behind it. Your contractor and your tile setter settle all of that, and it is far cheaper to raise before the tile than to work around after.

If the layout is staying put and you are putting better glass back into the opening you already have, that is shower door replacement and your tile never gets touched. If the tub is staying and the remodel is happening around it, bathtub shower doors handle that opening. Where a swinging door would collide with a vanity in a tight hall bath, sliding shower doors keep the floor clear, and a framed shower door is still the sensible answer in plenty of rooms. Everything we build for this city sits on the Rochester shower doors page.

How we work with you

Living In The House While It Happens

01

One Bathroom, Whole Household

When the room being remodeled is the only full bath, every day it is down is felt by everyone. That is the strongest argument for choosing your glass and hardware before tile even starts, so the measure can happen the day the grout is finished instead of a week later while somebody is still deciding on a finish.

02

Talk To Your Tile Setter

Ask for a level curb, jambs kept square and walls as plumb as the substrate allows. Nobody delivers a perfect bathroom and we cut glass for real walls every day. Still, the small things asked for before tile goes up produce a better looking door than the same things noticed after the grout has cured.

03

The Old Enclosure Leaves With Us

When something is already in the opening, the old door and its frame come out on install day and go with our truck. You are not stacking a rusted frame beside the driveway, working out how to get tempered glass into a bin, or adding another disposal run to a project that has plenty already.

Shower enclosure by Fortune Shower Doors in a Rochester, Michigan bathroom
Sequencing

What To Have Ready Before We Measure

The measure moves faster and the quote gets sharper when a few things are already decided. Know the fixture finish you are putting in, because the shower hardware has to sit next to it for years. Know what the door has to clear, since a vanity, a toilet or a linen closet door can decide the style on its own. Know how the room gets used, because a house with kids and a house with two adults want different things from the same opening. And if you are texting photos ahead, one wide shot of the whole bathroom tells us more than five close-ups of the old track.

Sequencing is the other half. If a general contractor is running your job, tell us and we will coordinate the measure and the install directly with them, so you are not carrying messages between two trades. If you are running it yourself, the stretch to protect is the end: tile finishes, we measure, your glass gets built for your opening, then we install. We will tell you what that looks like once we have stood in the room. What we will not do is invent a date over the phone, because a number promised before anyone has seen the bathroom is how the end of a remodel goes sideways.

  • Glass and hardware chosen before tile begins
  • Curb level, jambs square, walls as plumb as possible
  • Measure booked for the day grout is finished
  • Door swing checked against vanity, toilet and doors
  • One wide photo of the whole bathroom, texted ahead
  • Old enclosure pulled out and hauled away by us
Good Questions

Common questions.

When in my remodel should I call you?

Early for the conversation, late for the measure. A call before tile goes in lets us flag curb height, door swing and blocking while your contractor can still act on any of it. The measure itself waits until tile and grout are finished, because that is the opening your glass gets cut to, and nothing before it is real.

Can I order the door at the same time as the tile?

No, and this is the most common misunderstanding on a remodel. Tile changes the finished dimension of the opening on every surface it touches, so glass ordered beforehand is glass ordered against a guess. We measure the completed space and cut panels to it. Choosing your glass and hardware early is useful. Ordering early is not.

How long is my bathroom out of service waiting on glass?

Usually the room is back in use before the glass shows up, since the door is the last thing in and not the thing holding up plumbing, tile or the vanity. How long the glass itself takes depends on the enclosure, and we will tell you what to expect at the measure rather than guessing while your bathroom is still torn apart.

The tile is done but the plumber has not set the trim yet. Can you measure?

We would rather measure with the valve trim and the shower head already in place. They tell us where the spray lands relative to the door and whether a lever will end up fighting a pull or a towel bar. If the tile is finished and the trim is still to come, say so when you book and we will plan the visit around it rather than measure twice.

My contractor is running the job. Should he call, or should I?

Either, as long as we know the answer. Tell us who to coordinate the measure and the install with, and who makes the final call on glass and hardware, because those are often two different people. Many homeowners choose the glass themselves and leave the scheduling to their contractor, and that works well when everyone knows it up front.

How late can I change the glass or the hardware finish?

Selections have to be settled before fabrication begins, since nothing in your enclosure is pulled off a shelf. Once a piece is in the shop, changing your mind means starting that piece again. Decide at the measure if you can, which is exactly why we bring glass and hardware samples into your bathroom instead of asking you to picture them.

Rochester, MI

Book The Measure For The Day The Grout Is Done

Call (586) 315-8900 or text (586) 800-9481 with a photo of the bathroom and where the project stands. The in-home measure is free and there is no pressure.